Andheri – Versova- Ghatkopar Route under construction


The work has not even commenced in almost 3km of stretch (Out of total 11.02km) till date




Western Express Highway Station:
·         Half the width of Western Express Highway station under const.
·         Columns for via ducts in the middle of arterial roads
·         Out of 457 columns for via ducts, only 279 columns have come up above ground level and about 2.4 km length of via duct out of 11.02km is installed over these columns till date