As the name suggests, this blog is about saving the suburbs of Mumbai from the disaster of the elevated metro routes. This blog aims at responding to the media, and demystifying the reality of the upcoming Versova-Andheri-Ghatkopar(VAG) Metro and the other 8 routes too. We seek to bring you the real facts, figures and true stories. Here’s our answer to MMRDA, here’s our support towards Mumbai’s future. Join in, log on to the dedicated website: http://www.saveoursuburbs.in/
Tuesday, October 19, 2010
RESPONSE ON "CENTRE REFUSES FUNDS FOR COLABA TO BANDRA METRORAIL"
LINE III: COLABA TO BANDRA METRORAIL:
Hindustan Times -16th Oct 2010
DNA – 16th Oct, 2010
As expected – it is happening – Mumbaikars will never see the 3rd line of Metro between Colaba to Bandra – Now Centre says ‘No’ to subsidies required for ` 12000 Crores Project.
It is perplexing that no PPP partner came forward after 1st and 2nd line awarded to Reliance Infra. Although the ridership would be 43% between Bandra /Colaba, on this route, compared to 16% between Bandra / Mankhurd.
Consider the Following equation:
COST OF 3rd LINE (20 km route) | 10km Underground 10km Elevated | @ @ | ` 600/- Cr./Km. ` 200/- Cr./Km. | ` 4000/- Cr. ` 2000/- Cr. ` 8000/- Cr. | ` 400 Cr./Km. |
COST OF 2 nd LINE (32 km route) | Fully Elevated | | | ` 11,500/- Cr. | ` 360 Cr./Km. |
Now let the Citizens decide whether it is justified to spend `11,500 /- Crores. When the entire project is heading towards bankruptcy OR invest marginally higher amount of ` 40 Cr./Km. which shall be beneficial for the city of Mumbai for next 100 years.