Monday, September 27, 2010

Facts on the new completion date of “Aug 2011” for the VAG route









The Facts on the new completion date of “Aug 2011” for the VAG route
  • Of the 12 stations only 3 have reached slab level
  • Of the 450 pillars for the track only 247 are ready today
  •  No clarity on the design yet, on the bridge over the railway
  • Over 3KMS of the VAG route, MMRDA- Reliance have no access too yet
  • Of the stations that have reached the slab level, the fire dept have refused an NOC…

There is no way this quantum of work can be completed in the next 11 months.

Is this another common wealth like situation? this is not about Juhu or pushing for the underground but a reality check!!

Kind regards
Sherley J Singh


1 comment:

  1. Questions TO MMRDA

    How much time they took for completed work as narreted above?
    What is Individual time frame set for each uncomplete work narreted above?

    Already deadline extended couple of times. If they cannot complete work in next eleven months who will take onus?

    At CWG few were sacked. Will Somebody take responsibility at MMRDA or will they wait till they are sacked?

    ReplyDelete